Statement
Implement the 3x3x3x1 permit system (3 days renos, 3 weeks single-family/townhomes, 3 months mid-rise, 1 year high-rise).
Overview
Implement the 3x3x3x1 permit system (3 days renos, 3 weeks single-family/townhomes, 3 months mid-rise, 1 year high-rise).
Sources
-
Daily Hive reported in September 2026 that 92% of simple renovation permits were issued within three days, but single-detached homes still took 160 days, multi-family and mid-rise projects 9.8 months, and the 3x3x3x1 system had not yet been achieved.
-
The City report describes the 3-3-3-1 permitting dashboard and tracks progress toward the target processing times, while noting significant complexity in the permitting process.
-
Implement the 3x3x3x1 permit system (3 days renos, 3 weeks single-family/townhomes, 3 months mid-rise, 1 year high-rise).
-
New multi-family and detached custom construction projects continue to experience timelines well beyond the 3-week and 3-month metrics.
Timeline
-
Daily Hive reported in September 2026 that 92% of simple renovation permits were issued within three days, but single-detached homes still took 160 days, multi-family and mid-rise projects 9.8 months, and the 3x3x3x1 system had not yet been achieved.
View source
-
The City report describes the 3-3-3-1 permitting dashboard and tracks progress toward the target processing times, while noting significant complexity in the permitting process.
View source
-
Implement the 3x3x3x1 permit system (3 days renos, 3 weeks single-family/townhomes, 3 months mid-rise, 1 year high-rise).
View source
-
New multi-family and detached custom construction projects continue to experience timelines well beyond the 3-week and 3-month metrics.
View source