Statement
An ABC Majority will eliminate the city’s housing construction backlog (which will help increase the supply of market, non-market, and supportive housing) with a 3x3x3x1 permit approval system, whereby it will take: – Three days to approve home renovations (including renovations to accommodate mobility and accessibility-related challenges) – Three weeks to approve single-family homes and townhouses – Three months to approve professionally designed multi-family and mid-rise projects where existing zoning is already in place – One year (down from six years) to approve a high-rise or large-scale project
Overview
Permitting processing times and backlogs did not achieve the promised 3-day, 3-week, 3-month, and 1-year timeline benchmarks, despite ongoing administrative and digital modernization efforts.
Sources
-
Daily Hive reported in September 2026 that 92% of simple renovation permits were issued within three days, but single-detached homes still took 160 days, multi-family and mid-rise projects 9.8 months, and the 3x3x3x1 system had not yet been achieved.
-
The City report describes the 3-3-3-1 permitting dashboard and tracks progress toward the target processing times, while noting significant complexity in the permitting process.
-
An ABC Majority will eliminate the city's housing construction backlog (which will help increase the supply of market, non-market, and supportive housing) with a 3x3x3x1 permit approval system, whereby it will take: \u2013 Three days to approve home renovations (including renovations to accommodate mobility and accessibility-related challenges) \u2013 Three weeks to approve single-family homes and townhouses \u2013 Three months to approve professionally designed multi-family and mid-rise projects where existing zoning is already in place \u2013 One year (down from six years) to approve a high-rise or large-scale project.
-
New multi-family and detached custom construction projects continue to experience timelines well beyond the 3-week and 3-month metrics.
Timeline
-
Daily Hive reported in September 2026 that 92% of simple renovation permits were issued within three days, but single-detached homes still took 160 days, multi-family and mid-rise projects 9.8 months, and the 3x3x3x1 system had not yet been achieved.
View source
-
The City report describes the 3-3-3-1 permitting dashboard and tracks progress toward the target processing times, while noting significant complexity in the permitting process.
View source
-
An ABC Majority will eliminate the city's housing construction backlog (which will help increase the supply of market, non-market, and supportive housing) with a 3x3x3x1 permit approval system, whereby it will take: \u2013 Three days to approve home renovations (including renovations to accommodate mobility and accessibility-related challenges) \u2013 Three weeks to approve single-family homes and townhouses \u2013 Three months to approve professionally designed multi-family and mid-rise projects where existing zoning is already in place \u2013 One year (down from six years) to approve a high-rise or large-scale project.
View source
-
New multi-family and detached custom construction projects continue to experience timelines well beyond the 3-week and 3-month metrics.
View source